Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Apr 2024 Work in progress | 81% Completed | 11/04/2024 Supplied total -84.753km, Laid Total-73KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
05 Apr 2024 Work in progress | 81% Completed | 05/04/2024 Supplied total -84.753km, Laid Total-73KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
30 Mar 2024 Work in progress | 81% Completed | 30/03/2024 Supplied total -84.753km, Laid Total-73KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68628m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
01 Mar 2024 upplied total -84.753km, Laid Total-72.831KM,/out of 90km , HTC -2077 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
23 Feb 2024 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , HTC -2075 out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
15 Feb 2024 Work in progress | 78% Completed | 15/02/2024 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , FHTC -2467out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
29 Nov 2023 Work in progress | 78% Completed | 29/11/2023 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , FHTC -2467out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
03 Nov 2023 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , FHTC -2467out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
13 Oct 2023 Work in progress | 78% Completed | 13/10/2023 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , FHTC -2467out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2
28 Sep 2023 Work in progress | 78% Completed | 28/09/2023 Supplied total -84.753km, Laid Total-72.831KM,/out of 90km , FHTC -2467out of 4422Nos 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --68468m . Pipe Laid length. 1).110mm PVC—7.757k m. 2).90mm PVC—45.6006km, 3). 140mm pvc-2.105 4).160mm PVC,6kg—2.390 km 5),250mm DI K9-1946.80 m 6).350mm DI K9-210m 7) 200mm DI-300M, 8)300 mm DI-118M 9)125mm DI-12M 10)400 mm DI-6M (4th bill-170 FHTC provided) Chittur Project Dn - AE 2