Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Oct 2022 Work in progress | 75% Completed | 20/10/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -2142, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided) Chittur Project Dn - AE 2
14 Oct 2022 Work in progress | 75% Completed | 14/10/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -2000, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
08 Oct 2022 Work in progress | 75% Completed | 08/10/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1758, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
07 Oct 2022 Work in progress | 75% Completed | 07/10/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1859, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
29 Sep 2022 Work in progress | 75% Completed | 29/09/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1758, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) View all updates Chittur Project Dn - AE 2
21 Sep 2022 Work in progress | 75% Completed | 21/09/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1625, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
10 Sep 2022 Work in progress | 75% Completed | 10/09/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1278, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided)) Chittur Project Dn - AE 2
01 Sep 2022 Work in progress | 75% Completed | 01/09/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1278, 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M(4th bill-170 FHTC provided) Chittur Project Dn - AE 2
25 Aug 2022 Work in progress | 74% Completed | 25/08/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1119 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M Chittur Project Dn - AE 2
21 Aug 2022 Work in progress | 74% Completed | 21/08/2022 Supplied total -84.753km, Laid Total-61.222 KM, FHTC -1119 1). 400mm DI --35 m. 2).350mm DI -- 250m 3). 300mm DI--425m 4).250mm DI---1949m 5).200mmDI---1306m 6).160mm PVC,6kg--3735m 7).140mm PVC, 6kg---3820m 8).110mm PVC,6kg --9028m 9).90mm PVC,6kg --64205m . Pipe Laid length. 1).110mm PVC—7.340k m. 2).90mm PVC—42.516km, 3). 140mm pvc-2.096 4).160mm PVC,6kg—2.300 km 5),250mm DI K9-1932 m 6).350mm DI K9-210m 7) 200mm DI-250M, 8)300 mm DI-118M Chittur Project Dn - AE 2