Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | Work Tendered 2 times. Re-casted Once and retendered. No one participated. Put for retendering. LA payment deposited at Dist. Collectorate. | Thiruvananthapuram Project AE5 | |
13 Feb 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
12 Feb 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
06 Feb 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
05 Feb 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
20 Jan 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
16 Jan 2024 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
21 Dec 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
12 Dec 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
04 Dec 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 |