Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress. | Thiruvananthapuram Project AE5 | |
27 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
26 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
22 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
19 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
15 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
11 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
10 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
04 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 | |
03 Jul 2023 | Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress | Thiruvananthapuram Project AE5 |