KIIFB Project: Tranche 21: WRD025-08: Development activities of Drinking Water Project at Mudakkal Panchayath - Augmentation and Rehabilitation of RWSS to Mudakkal Panchayath

Project KIIFB Project: Tranche 21: WRD025-08: Development activities of Drinking Water Project at Mudakkal Panchayath - Augmentation and Rehabilitation of RWSS to Mudakkal Panchayath
Project Code TVMKIIFB032210763
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description The project include Installation of RW Pumps in existing well cum pump house at Ayilam, laying of 400mm DI RWPM for appx. 770m, Construction of a 6 MLD WTP at Ayilam, Installation of CW Pumps in WTP, Laying of 400mm DI K9 CWPM for approx. 4212m to proposed 19 LL OHSR at Nedupuram, laying of 100mm DI K9 for apprx. 1735m upto existing OHSR at Aryiankunnu, Construction of 19LL OHSR at Nedumpuram and laying of 90 mm PVC to 160mm PVC and 150mm DI to 500mm DI for Distribution and Transmission purposes.
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 400784013
AS Number WRD025-08/APR-6/2022/KIIFB
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD 6.00
Actual Project Completion Date Date is not specified
Coverage Mudakkal Panchayath

Packages

No. Project Name Location View
1 Construction of a Check Dam Across Vamanapuram River near Tachoorkunnu, Attingal Trivandrum Project Dn
2 KIIFB Project: Tranche 21: WRD025-08: Development activities of Drinking Water Project at Mudakkal Panchayath - Augmentation and Rehabilitation of RWSS to Mudakkal Panchayat Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 Work Tendered 2 times. Re-casted Once and retendered. No one participated. Put for retendering. LA payment deposited at Dist. Collectorate. Thiruvananthapuram Project AE5
13 Feb 2024 Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress Thiruvananthapuram Project AE5
12 Feb 2024 Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress Thiruvananthapuram Project AE5
06 Feb 2024 Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress Thiruvananthapuram Project AE5
05 Feb 2024 Revised GO for LA received from Revenue (B) Dept. 4 (1) Notification issued. SIA study in progress Thiruvananthapuram Project AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/03/2022
Scheduled date of Completion of the Project 31 Dec 2023
Expected date of Completion 31/12/2023