Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Nov 2021 | 300mm DI K9 pipe -5047.5m laying completed. Balance work in progress | Chittur PH Sub Dn AEE | |
25 Sep 2021 | First bill submitted 0.97Cr second bill submitted 2.19Cr . | Chittur PH Sub Dn AEE | |
25 Sep 2021 | 2.5KM Pipes laid | Palakkad PH Dn EE | |
10 Jul 2021 | Pipe supplied -8602m (300mm DI K9 pipe). First and Part bill submitted to Division | Chittur PH Sub Dn AEE | |
25 Feb 2021 | WBS preparartion in progress | Nenmara Sn AE | |
07 Feb 2021 | WBS preparartion in progress. | Chittur PH Sub Dn AEE | |
06 Feb 2021 | Response received from the Contractor | Nenmara Sn AE | |
06 Feb 2021 | Response received from the Contractor | Nenmara Sn AE | |
06 Feb 2021 | Response received from Contractor | Nenmara Sn AE | |
06 Feb 2021 | Response received from Contractor | Nenmara Sn AE |