Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Apr 2024 | Pipes supllied, 8 Km of pipeline laid, 260 nos of HTCs given | Koothuparambu PH Sn AE | |
19 Mar 2024 | Pipes supllied, 7 Km of pipeline laid, 241 nos of HTCs given. | Koothuparambu PH Sn AE | |
19 Mar 2024 | Pipes supllied,7 Km of pipeline laid, 241 nos of HTCs given, PWD road permission awaited | Koothuparambu PH Sn AE | |
12 Mar 2024 | Pipes supllied, 6.3 Km of pipeline laid, 239 nos of HTCs given, PWD road permission awaited. | Koothuparambu PH Sn AE | |
29 Feb 2024 | Pipes supllied, 5.5 Km of pipeline laid, 27 nos of HTCs given, Waiting for PWD road permission | Koothuparambu PH Sn AE | |
21 Feb 2024 | Pipes supllied, 5.5 Km of pipeline laid, 27 nos of HTCs given, Waiting for PWD road permission | Koothuparambu PH Sn AE | |
13 Feb 2024 | Pipes supllied, 5.5 Km of pipeline laid, 27 nos of HTCs given | Koothuparambu PH Sn AE | |
08 Feb 2024 | Pipes supllied, 5.5 Km of pipeline laid, 25 nos of HTCs given | Koothuparambu PH Sn AE | |
29 Jan 2024 | Pipes supllied, 5 Km of pipeline laid, 20 nos of HTCs given. | Koothuparambu PH Sn AE | |
29 Dec 2022 | Work completed | Thalassery AEE |