Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jul 2021 | Supply order placed | Kozhikode Project Dn AE5 | |
15 Jul 2021 | Supply order placed | Kozhikode Project Dn AE5 | |
14 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
12 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
09 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
07 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
05 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
02 Jul 2021 | Materials ordered | Kozhikode Project Dn AE5 | |
28 Jun 2021 | materials ordered | Kozhikode Project Dn AE5 | |
21 Jun 2021 | materials ordered | Kozhikode Project Dn AE5 |