Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jan 2022 Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1143.5m, 2)500mm-3589.65m, 3)250mm-3308.75m, Total laid: 8041.90 m. Kozhikode Project Dn AE5
30 Dec 2021 Pipe supplied 1)500mm DI -6149m 2)250 mm DI - 5500 m 3)600 mm DI -1914m 4)300mmDI-462m 5)450mm DI-3113m Total pipe supplied = 17138m. Laying work in progress- 1)600mm-954.80m, 2)500mm-3523.65m, 3)250mm-3047.05m. Total laid: 7525.50 m Kozhikode Project Dn AE5
20 Dec 2021 Pipe supplied 1)500mm DI -6149m 2)250 mm DI - 5500 m 3)600 mm DI -1914m 4)300mmDI-462m 5)450mm DI-3113m Total pipe supplied = 17138m. Laying work in progress- 1)600mm-544.50m, 2)500mm-3276.15m, 3)250mm-2480.9m. Total laid:6301.55 m Kozhikode Project Dn AE5
13 Dec 2021 Pipe supplied 1)500mm DI -6149m 2)250 mm DI - 5500 m 3)600 mm DI -1914m 4)300mmDI-462m 5)450mm DI-3113m Total pipe supplied = 17138m. Laying work in progress- 1)600mm-339.70m, 2)500mm-2784m, 3)250mm-1989.05m. Total laid: 5112.75 m Kozhikode Project Dn AE5
04 Dec 2021 Pipe supplied 1)500mm DI -6149m 2)250 mm DI - 5500 m 3)600 mm DI -1914m 4)300mmDI-462m 5)450mm DI-3113m Total pipe supplied = 17138m ,Laying work in progress- 600mm-237.65m, 500mm-1999.85m, 250mm-1314m. Total laid: 3551.5 m Kozhikode Project Dn AE5
24 Nov 2021 CC 1st &part bill paid to contractor on 22.11.2021 and CC 2st &part bill submitted on 23.11.2021, amount of Rs.35916804.Pipe supplied 1)500mm DI -5934m 2)250 mm DI - 5500 m 3)600 mm DI -803m 4)300mmDI-368m 5)450mm DI-3113m Total pipe supplied = 15719m Laying work in progress- 600mm-204m, 500mm-1205m, 250mm-587m. Kozhikode Project Dn AE5
18 Nov 2021 Pipe supplied 1)500 mm DI -3025m 2)250 mm DI - 5500 m 3)600 mm DI -803m Total pipe supplied = 9328m ,Laying work in progress-600m completed Kozhikode Project Dn AE5
06 Nov 2021 cc 1st &part bill submitted amount of 39162361/-, Laying work in progress Kozhikode Project Dn AE5
30 Oct 2021 cc 1st &part bill prepared, for amount of 39162361/- , Laying work in progress Kozhikode Project Dn AE5
26 Oct 2021 Laying work started, PWD RC permission pending for Kallode to Perambra road 3 KM ( application was rejected due to DLP ) the Restoration work is included in KWA 's scope, Supply of material in progress, 500 mm DI -3025m, 250 mm DI - 5500 m ,600 mm DI -803 m supplied. Kozhikode Project Dn AE5