Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Mar 2022 |
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1690.05 m, 2)500mm - 6145.37m ,3) 450mm -680m, 4)250mm- 5225.5m, Total laid: 13740.92 m .
|
Kozhikode Project Dn AE5 |
|
02 Mar 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-4103m ,Total pipe supplied = 18128m. Pipe laid - 1)600mm-1659.05 m, 2)500mm - 6008.52m ,3) 450mm -485.5m, 4)250mm- 5160.8m, Total laid: 13313.87 m .
|
Kozhikode Project Dn AE5 |
|
24 Feb 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-4103m ,Total pipe supplied = 18128m. Pipe laid - 1)600mm-1659.05 m, 2)500mm - 5923.02m ,3) 450mm -115.5m, 4)250mm- 5132.5m, Total laid: 12830.07 m .
|
Kozhikode Project Dn AE5 |
|
14 Feb 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-4103m ,Total pipe supplied = 18128m. Pipe laid - 1)600mm-1648.05 m, 2)500mm - 5558.42m , 3)250mm- 4962.50m, Total laid: 12168.97 m .
|
Kozhikode Project Dn AE5 |
|
02 Feb 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-4103m ,Total pipe supplied = 18128m. Pipe laid - 1)600mm-1780 m, 2)500mm - 5196.77m , 3)250mm- 4847.3m, Total laid: 11824.07 m .
|
Kozhikode Project Dn AE5 |
|
01 Feb 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1780 m, 2)500mm - 5148.27m , 3)250mm- 4811.5 m, Total laid: 11739.77 m .
|
Kozhikode Project Dn AE5 |
|
29 Jan 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1780 m, 2)500mm-4750.27, 3)250mm-4452m, Total laid: 10982.27 m
|
Kozhikode Project Dn AE5 |
|
18 Jan 2022 |
CC 3rd and part bill submitted , amount RS.33752347/-. Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1615.05 m, 2)500mm-4179m, 3)250mm-4083.05m, Total laid: 9878 m |
Kozhikode Project Dn AE5 |
|
13 Jan 2022 |
CC 3rd and part bill prepared , amount RS.33752347/-. Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1437.70 m, 2)500mm-3739.55m, 3)250mm-3680.05m, Total laid: 8857.30 m. |
Kozhikode Project Dn AE5 |
|
11 Jan 2022 |
Pipe supplied- 1)500 mm DI -6149m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-462m, 5)450mm DI-3113m Total pipe supplied = 17138m. Pipe laid - 1)600mm-1437.70 m, 2)500mm-3739.55m, 3)250mm-3680.05m, Total laid: 8857.30 m. |
Kozhikode Project Dn AE5 |
|