Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR

Project KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR
Project Code CLTKIIFB03196093
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying, Laying, Testing and commissioning of Supplying Laying testing and commissioning of 600mmDI K9-1897m 500mm DI K9-7686m 450mm DI K9 -4147m 300mm DI K9 -550m- Replacement of existing Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR (14280m) Supplying Laying testing and commissioning of 250mmDI K9-5500m Replacement of existing Distribution main from Peruvannamuzhi Treatment Plant to Koothali GP and Changaroth GP
Status Completed
District Kozhikkode
Executing Office Kozhikode Project Dn
AS Amount (Rs) 182270000
AS Number WRD005-130-PA-01
TS Amount (Rs) 182200000
TS Number TS/2020-2021/2020/28220
Total Bill Submitted (Rs) 179780996
Total Bill Paid (Rs) 179780996
Population Benefitted 34908
Capacity in MLD 12.00
Actual Project Completion Date 28 Feb 2023
Coverage Perambra Panchayath,changaroth ,Koothali
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB (TRAN2-WRD 005-130) - RENOVATION OF WSS TO PERAMBRA, KOOTHALI, CHAKKITTAPARA AND CHANGAROTH PANCHAYATHS Kozhikode Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Feb 2023 Work completed. Kozhikode Project Dn AE5
26 Feb 2023 Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed and Charging work completed. Road reformation work in progress. Kozhikode Project Dn AE5
30 Jan 2023 Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed. work in progress. Kozhikode Project Dn AE5
23 Jan 2023 Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7333.27m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19062.67m,work in progress. Kozhikode Project Dn AE5
18 Jan 2023 Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7325.77m ,3) 450mm -3793.3m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 18966.77m,work in progress. Kozhikode Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/05/2021
Scheduled date of Completion of the Project 04 Feb 2022
Expected date of Completion 28/02/2023

Processing Dates

AS Date 23 Mar 2019
TS Date 24 Dec 2020

Other details

Project Officers View