KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR
Project |
KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR |
Project Code |
CLTKIIFB03196093 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supplying, Laying, Testing and commissioning of Supplying Laying testing and commissioning of
600mmDI K9-1897m
500mm DI K9-7686m
450mm DI K9 -4147m
300mm DI K9 -550m-
Replacement of existing Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR (14280m)
Supplying Laying testing and commissioning of 250mmDI K9-5500m
Replacement of existing Distribution main from Peruvannamuzhi Treatment Plant to Koothali GP and Changaroth GP
|
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
182270000
|
AS Number |
WRD005-130-PA-01 |
TS Amount (Rs) |
182200000 |
TS Number |
TS/2020-2021/2020/28220 |
Total Bill Submitted (Rs) |
179780996 |
Total Bill Paid (Rs) |
179780996 |
Population Benefitted |
34908 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
28 Feb 2023 |
Coverage |
Perambra Panchayath,changaroth ,Koothali |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB (TRAN2-WRD 005-130) - RENOVATION OF WSS TO PERAMBRA, KOOTHALI, CHAKKITTAPARA AND CHANGAROTH PANCHAYATHS |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Feb 2023 |
Work completed.
|
Kozhikode Project Dn AE5 |
|
26 Feb 2023 |
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed and Charging work completed. Road reformation work in progress.
|
Kozhikode Project Dn AE5 |
|
30 Jan 2023 |
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed. work in progress.
|
Kozhikode Project Dn AE5 |
|
23 Jan 2023 |
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7333.27m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19062.67m,work in progress.
|
Kozhikode Project Dn AE5 |
|
18 Jan 2023 |
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7325.77m ,3) 450mm -3793.3m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 18966.77m,work in progress. |
Kozhikode Project Dn AE5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/05/2021 |
Scheduled date of Completion of the Project |
04 Feb 2022 |
Expected date of Completion |
28/02/2023 |
Processing Dates
AS Date |
23 Mar 2019 |
TS Date |
24 Dec 2020 |