Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Apr 2023 | 17km pipe line laid(160mm,110mm &90mm HDPE Pipe and 75mm,63mm&50mm PVC Pipe) | Nattika Project Dn | |
05 Apr 2023 | Work started and 15 km pipe line laid | Nattika Project Dn | |
04 Apr 2023 | Work started and 15 km pipe line laid | Nattika Project Dn | |
03 Apr 2023 | Work started and 12 km pipe line laid | Nattika Project Dn | |
02 Apr 2023 | Work started and 12 km pipe line laid | Nattika Project Dn | |
01 Apr 2023 | Work started and 8 km pipe line laid | Nattika Project Dn | |
31 Mar 2023 | Work started and 8 km pipe line laid | Nattika Project Dn | |
30 Mar 2023 | Work started and 8 km pipe line laid | Nattika Project Dn | |
29 Mar 2023 | Work started and 8 km pipe line laid | Nattika Project Dn | |
28 Mar 2023 | Work started and 8 km pipe line laid | Nattika Project Dn |