27 Oct 2023 69850 Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1533 Nos. out of 5724 FHTC Nattika Project Dn
16 Oct 2023 67238m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1329 Nos. out of 5724 FHT Nattika Project Dn
13 Oct 2023 66496m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1216 Nos. out of 5724 FHTC Nattika Project Dn
10 Oct 2023 65342m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1157 Nos. out of 5724 FHTC Nattika Project Dn
05 Oct 2023 64140m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1101 Nos. out of 5724 FHTC Nattika Project Dn
20 Sep 2023 62279m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 939 Nos. out of 5724 FHTC Nattika Project Dn
10 Sep 2023 60340m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 802Nos. out of 5724 FHTC Nattika Project Dn
03 Sep 2023 59009m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 722 Nos. out of 5724 FHTC Nattika Project Dn
21 Aug 2023 56736m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 688 Nos. out of 5724 FHTC Nattika Project Dn
09 Aug 2023 52538m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 678 Nos. out of 5724 FHTC. Nattika Project Dn