Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Oct 2023 |
69850 Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1533 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
16 Oct 2023 |
67238m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1329 Nos. out of 5724 FHT |
Nattika Project Dn |
|
13 Oct 2023 |
66496m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1216 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
10 Oct 2023 |
65342m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1157 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
05 Oct 2023 |
64140m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1101 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
20 Sep 2023 |
62279m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 939 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
10 Sep 2023 |
60340m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 802Nos. out of 5724 FHTC |
Nattika Project Dn |
|
03 Sep 2023 |
59009m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 722 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
21 Aug 2023 |
56736m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 688 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
09 Aug 2023 |
52538m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 678 Nos. out of 5724 FHTC. |
Nattika Project Dn |
|