15 Feb 2024 86828m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2424/5724 Nos. HTC given = 2560 Nos. Construction of 14.5 GLSR-Site clearance completed. Nattika Project Dn
12 Feb 2024 86814m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2401/5724 Nos. HTC given = 2535 Nos. Construction of 14.5 GLSR-Site clearance completed. Nattika Project Dn
08 Feb 2024 86512m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2401/5724 Nos. HTC given = 2524 Nos Nattika Project Dn
21 Jan 2024 85145m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2394/5724 Nos. HTC given = 2484Nos. Construction of GLSR-Site clearance completed Nattika Project Dn
19 Jan 2024 85026m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2388/5724 Nos. HTC given = 2481Nos. Construction of GLSR-Site clearance completed Nattika Project Dn
18 Jan 2024 84831m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2370/5724 Nos. HTC given = 2477Nos. Construction of GLSR-Site clearance completed Nattika Project Dn
10 Jan 2024 83215m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2301/5724 Nos. HTC given = 2430 Nos. Construction of GLSR-Site clearance completed Nattika Project Dn
10 Jan 2024 83215 m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2301/5724 Nos. HTC given = 2430 Nos. Nattika Project Dn
05 Jan 2024 82600m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2238/5724 Nos.HTC given = 2368 Nos. Construction of GLSR-Site clearence completed Nattika Project Dn
21 Dec 2023 81273m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 2138Nos. out of 5724 FHTC Nattika Project Dn