Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2024 |
86828m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2424/5724 Nos. HTC given = 2560 Nos. Construction of 14.5 GLSR-Site clearance completed. |
Nattika Project Dn |
|
12 Feb 2024 |
86814m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2401/5724 Nos. HTC given = 2535 Nos. Construction of 14.5 GLSR-Site clearance completed. |
Nattika Project Dn |
|
08 Feb 2024 |
86512m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2401/5724 Nos. HTC given = 2524 Nos |
Nattika Project Dn |
|
21 Jan 2024 |
85145m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2394/5724 Nos. HTC given = 2484Nos. Construction of GLSR-Site clearance completed |
Nattika Project Dn |
|
19 Jan 2024 |
85026m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2388/5724 Nos. HTC given = 2481Nos. Construction of GLSR-Site clearance completed |
Nattika Project Dn |
|
18 Jan 2024 |
84831m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2370/5724 Nos. HTC given = 2477Nos. Construction of GLSR-Site clearance completed |
Nattika Project Dn |
|
10 Jan 2024 |
83215m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2301/5724 Nos. HTC given = 2430 Nos. Construction of GLSR-Site clearance completed |
Nattika Project Dn |
|
10 Jan 2024 |
83215 m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2301/5724 Nos. HTC given = 2430 Nos. |
Nattika Project Dn |
|
05 Jan 2024 |
82600m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). Geo Tagging- 2238/5724 Nos.HTC given = 2368 Nos. Construction of GLSR-Site clearence completed |
Nattika Project Dn |
|
21 Dec 2023 |
81273m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 2138Nos. out of 5724 FHTC |
Nattika Project Dn |
|