Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2023 |
80985m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 2128Nos. out of 5724 FHTC |
Nattika Project Dn |
|
19 Dec 2023 |
80679m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 2113Nos. out of 5724 FHTC |
Nattika Project Dn |
|
07 Dec 2023 |
78066m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1996 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
06 Dec 2023 |
77675m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1990 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
30 Nov 2023 |
76378m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1941Nos. out of 5724 FHTC |
Nattika Project Dn |
|
29 Nov 2023 |
75976m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1941Nos. out of 5724 FHTC |
Nattika Project Dn |
|
16 Nov 2023 |
72815m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1857 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
05 Nov 2023 |
71781m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1800 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
02 Nov 2023 |
71093m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1630 Nos. out of 5724 FHTC |
Nattika Project Dn |
|
30 Oct 2023 |
70521m Pipe line laid-(90 mm HDPE,110 mm HDPE ,160 mm HDPE,75 mm PVC ,63 mm PVC ,50 mm PVC). HTC given = 1570 Nos. out of 5724 FHTC |
Nattika Project Dn |
|