| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...Sludge pump house plinth form work completed..,Centrifuge Building plinth beam rcc work completed & column starter form work , rcc work in progress..Blower foundation earth excavation work in progress. | Kollam Project HD | |
| 18 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...Sludge pump house plinth form work in progress. | Kollam Project HD | |
| 17 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Centrifuge building plinth beam Rcc work completed..Sludge pump house plinth form work in progress. | Kollam Project HD | |
| 16 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 15 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Centrifuge building plinth beam form work completed..Sludge pump house plinth bottom earth leveling work in progress(for pcc). | Kollam Project HD | |
| 15 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress..., | Kollam Project HD | |
| 14 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress..., Centrifuge building plinth beam form work in progress | Kollam Project HD | |
| 13 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress...,MBBR 4 walk way scaffolding work in progress... Centrifuge building plinth beam form work in progress | Kollam Project HD | |
| 12 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress...,MBBR 4 walk way scaffolding work in progress | Kollam Project HD | |
| 11 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Set out work completed for CCU building...,MBBR 4 walk way scaffolding work in progress | Kollam Project HD | |
| 10 Jan 2023 | 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress..., Centrifuge building plinth beam reinforcement work in progress | Kollam Project HD |