Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...Sludge pump house plinth form work completed..,Centrifuge Building plinth beam rcc work completed & column starter form work , rcc work in progress..Blower foundation earth excavation work in progress. Kollam Project HD
18 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...Sludge pump house plinth form work in progress. Kollam Project HD
17 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 18 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Centrifuge building plinth beam Rcc work completed..Sludge pump house plinth form work in progress. Kollam Project HD
16 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed & 2 components -above 50 % completed) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 15 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Centrifuge building plinth beam form work completed..Sludge pump house plinth bottom earth leveling work in progress(for pcc). Kollam Project HD
15 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress..., Kollam Project HD
14 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress..., Centrifuge building plinth beam form work in progress Kollam Project HD
13 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress...,MBBR 4 walk way scaffolding work in progress... Centrifuge building plinth beam form work in progress Kollam Project HD
12 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,CCU building pile point fixing work in progress...,MBBR 4 walk way scaffolding work in progress Kollam Project HD
11 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress...,Set out work completed for CCU building...,MBBR 4 walk way scaffolding work in progress Kollam Project HD
10 Jan 2023 10 components completed - 100% out of 34 components ( 5 components -above 90 % completed , 4 components - above 80 % completed ) ... for electro mechanical items - 23 factory inspection completed out of 32 items and 8 supplied at site..,Pre-Treatment unit Grit chamber Slab Reinforcement work in progress..., Centrifuge building plinth beam reinforcement work in progress Kollam Project HD