| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..Front drain sidewall rcc work completed...MBBR 1 & 2 connecting channel column concrete work completed..Centrifugal building reinforcement work in progress...Blower foundation reinforcement work in progress | Kollam Project HD | |
| 01 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..Front drain form work in progress...MBBR 1 & 2 connecting channel column reinforcement work in progress...Blower foundation reinforcement work... | Kollam Project HD | |
| 29 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor....MBBR 1 & 2 connecting channel column footing concrete work completed...Form work of drain in progress.... | Kollam Project HD | |
| 28 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor....MBBR 1 & 2 connecting channel column footing concrete work completed...Form work of drain in progress.... | Kollam Project HD | |
| 28 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor....Mcc room column final lift rcc completed...Blower foundation starter concrete work completed..Sludge pump foundation pcc completed..Manhole pcc completed.. | Kollam Project HD | |
| 27 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor.......Clarifier 1 launder slab form work and Front side drain side wall reinforcement work in progress...MCC room column final lift and.Blower foundation starter work in progress... | Kollam Project HD | |
| 26 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor.......Blower foundation raft rcc work completed..MCC room first lift column concrete completed... | Kollam Project HD | |
| 25 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 21 out of 37 supplied at site. termination notice / show cause notice send to contractor....MCC room column concrete work completed....Front side drain base concrete work completed.... | Kollam Project HD | |
| 24 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 21 out of 37 supplied at site. termination notice / show cause notice send to contractor | Kollam Project HD | |
| 23 Apr 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 21 out of 37 supplied at site...,CBSC , FBSC bottom slab form work in progress...,MCC Room Column Reinforcement work in progress | Kollam Project HD |