| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..Septage plant room block work in progress...Centrifugal building slab shuttering work in progress...Clarifier 2 laundry slab reinforcement work in progress..Pretreatment unit - screens slab cum beams reinforcement work in progress..Blower foundation concrete completed... | Kollam Project HD | |
| 11 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..Septage plant room block work in progress...Centrifugal building slab shuttering work in progress...Clarifier 2 laundry slab reinforcement work in progress..Pretreatment unit - screens slab cum beams reinforcement work in progress | Kollam Project HD | |
| 10 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor...Pretreatment unit - screens slab cum beams reinforcement work in progress....Blower foundation form work in progress...Manhole reinforcement work in progress...Clarifier 2 laundry slab reinforcement work in progress..Centrifugal building reinforcement work in progress. | Kollam Project HD | |
| 09 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor...Centrifugal building reinforcement work in progress...Clarifier 2 laundry slab reinforcement work ...Pretreatment unit - screens slab cum beams reinforcement work in progress...Grit chamber De shuttering work in progress... | Kollam Project HD | |
| 08 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor...MBBR 3 final lift and sidewall Rcc completed...Sludge pump house - pump foundation Rcc completed...Clarifier Launder slab rcc work completed ...Grit chamber sidewall final lift completed .. Curing progress...Clarifier 2 laundry slab reinforcement work in progress...MCC room roof slab work in progress...Fine screen chamber reinforcement work in progress... | Kollam Project HD | |
| 07 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor...Clarifier 2 launder form work in progress...Equalization tank walkway work started...MBBR final lift and sidewall Rcc work in progress...Pretreatment unit - screens slab cum beams reinforcement work in progress.. | Kollam Project HD | |
| 06 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..MBBR 1 & 2 connecting channel column-shuttering work in progress....FBSC & CBSC bottom slab and beam reinforcement work in progress...Clarifier 1 launder slab ready for rcc work ... | Kollam Project HD | |
| 05 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..MBBR 1 & 2 connecting channel column-shuttering work in progress....FBSC & CBSC bottom slab and beam reinforcement work in progress.... | Kollam Project HD | |
| 04 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..Front drain sidewall deshuttering work in progress...MBBR 1 & 2 connecting channel column-shuttering work in progress.... | Kollam Project HD | |
| 03 May 2023 | Civil work 11 out of 35 completed(Rcc work).Electro - Mechanical item 22 out of 37 supplied at site. termination notice / show cause notice send to contractor..centrifuge building -slab reinforcement and shuttering work in progress...Sludge drying bed -earth levelling work in progress...FBSC & CBSC screen channel shuttering work in progress.... | Kollam Project HD |