| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Mar 2023 | Work for piling work in progress - 15 piles out of 37 component..,Grit Chamber Side wall form work in progress..,Sludge drying bed side wall final lift form work in progress..,Clarifier 2 launder slab reinforcement & form work in progress..,Air Blower foundation earth excavation work in progress. | Kollam Project HD | |
| 13 Mar 2023 | Work for piling work in progress - 9 piles out of 37 component | Kollam Project HD | |
| 12 Mar 2023 | Amount remitted to GWD for hydraulic feasibility study on 9.03.2023.. Pilling work in progress for CCU building 6 completed | Kollam Project HD | |
| 11 Mar 2023 | Amount remitted to GWD for hydraulic feasibility study on 9.03.2023.. Pilling work in progress for CCU building | Kollam Project HD | |
| 11 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,CCU Building pile rcc work in progress. | Kollam Project HD | |
| 10 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,Sludge Thickner walk way hand rail fixing work in progress.CCU Building pile rcc work in progress. | Kollam Project HD | |
| 09 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Manhole chamber final lift side wall etc)..,CCU Building pile Rcc work in progress. | Kollam Project HD | |
| 08 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Manhole chamber final lift side wall etc)..,CCU Building pile steel making work in progress | Kollam Project HD | |
| 07 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,Sludge Thickner walk way hand rail fixing work in progress. | Kollam Project HD | |
| 06 Mar 2023 | Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab..,Man hole chamber 2 final lift side wall etc.Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress.Centrifuge Building slab form work in progress.Control unit pile foundation steel making work in progress. | Kollam Project HD |