Status Date Overall Project Status Project Officer Contact
14 Mar 2023 Work for piling work in progress - 15 piles out of 37 component..,Grit Chamber Side wall form work in progress..,Sludge drying bed side wall final lift form work in progress..,Clarifier 2 launder slab reinforcement & form work in progress..,Air Blower foundation earth excavation work in progress. Kollam Project HD
13 Mar 2023 Work for piling work in progress - 9 piles out of 37 component Kollam Project HD
12 Mar 2023 Amount remitted to GWD for hydraulic feasibility study on 9.03.2023.. Pilling work in progress for CCU building 6 completed Kollam Project HD
11 Mar 2023 Amount remitted to GWD for hydraulic feasibility study on 9.03.2023.. Pilling work in progress for CCU building Kollam Project HD
11 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,CCU Building pile rcc work in progress. Kollam Project HD
10 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,Sludge Thickner walk way hand rail fixing work in progress.CCU Building pile rcc work in progress. Kollam Project HD
09 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Manhole chamber final lift side wall etc)..,CCU Building pile Rcc work in progress. Kollam Project HD
08 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Manhole chamber final lift side wall etc)..,CCU Building pile steel making work in progress Kollam Project HD
07 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab....,Man hole chamber 2 final lift side wall etc)....Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress...,Centrifuge Building slab form work in progress...,Sludge Thickner walk way hand rail fixing work in progress. Kollam Project HD
06 Mar 2023 Bill released to the contractor for 2.36 crores.. labour force increased to 45 plus and work in good progress. RCC work for about 50 m3 is ready to be done ( MBBR IV final lift and walkway , Septage Tank ,Sludge pump house slab..,Man hole chamber 2 final lift side wall etc.Processes to start pile work of control unit are going on...,Clarifier 1 launder slab reinforcement work in progress.Centrifuge Building slab form work in progress.Control unit pile foundation steel making work in progress. Kollam Project HD