Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.19.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
09 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.18.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
08 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.17.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
07 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.16.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
06 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.15 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
05 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.13.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
04 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.12.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
03 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.11.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
02 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.10.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
01 Dec 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.9.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 |