Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
09 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
08 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
07 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
06 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
05 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
04 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
03 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
02 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
01 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 |