Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.1.5 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
19 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.1 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
18 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.1 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
17 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.Pipe laying in progress | Nattika Project Dn AE 6 | |
16 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.Pipe laying in progress | Nattika Project Dn AE 6 | |
15 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.Pipe laying in progress | Nattika Project Dn AE 6 | |
14 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.Pipe laying in progress | Nattika Project Dn AE 6 | |
13 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
12 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 | |
11 Nov 2022 | 90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied | Nattika Project Dn AE 6 |