Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m ,160mm PE Pipe-5178 m,75 mm PVC-4800 m, 63 mm PVC-4800 m & 50 mm PVC-2820 m supplied.26.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
19 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m ,160mm PE Pipe-5178 m,75 mm PVC-4800 m, 63 mm PVC-4800 m & 50 mm PVC-2820 m supplied.25.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
18 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m ,160mm PE Pipe-5178 m,75 mm PVC-4800 m, 63 mm PVC-4800 m & 50 mm PVC-2820 m supplied.25 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
17 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m ,160mm PE Pipe-5178 m,75 mm PVC-4800 m, 63 mm PVC-4800 m & 50 mm PVC-2820 m supplied.24 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
16 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m ,160mm PE Pipe-5178 m,75 mm PVC-4800 m, 63 mm PVC-4800 m & 50 mm PVC-2820 m supplied.23.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
15 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.22.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
14 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.21.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
13 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.20.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
12 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.19.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|
11 Dec 2022 |
90 mm PE pipe-45307 m,110mm PE Pipe-3015m,140mm PE Pipe-295m & 160mm PE Pipe-5178 m supplied.19.5 km pipe laying completed.Pipe laying in progress |
Nattika Project Dn AE 6 |
|