Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Dec 2023 90 km PVC Layed,35 number FHTC provided Thaliparamba WS Dn EE
22 Dec 2023 90 km PVC Layed Thaliparamba WS Dn EE
20 Dec 2023 86.99 km PVC Layed Thaliparamba WS Dn EE
18 Dec 2023 67 km PVC Layed Thaliparamba WS Dn EE
15 Dec 2023 67 km PVC Layed Thaliparamba WS Dn EE
13 Dec 2023 57 km PVC Layed Thaliparamba WS Dn EE
11 Dec 2023 48 km PVC Layed Thaliparamba WS Dn EE
08 Dec 2023 48 km PVC Layed Thaliparamba WS Dn EE
06 Dec 2023 40 km PVC Layed Thaliparamba WS Dn EE
04 Dec 2023 35 km PVC Layed Thaliparamba WS Dn EE