Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jan 2024 107.25km PVC Layed,115 number FHTC provided Thaliparamba WS Dn EE
17 Jan 2024 106.81 km PVC Layed,115 number FHTC provided Thaliparamba WS Dn EE
15 Jan 2024 105.55 km PVC Layed,115 number FHTC provided Thaliparamba WS Dn EE
11 Jan 2024 104.42 km PVC Layed,75 number FHTC provided Thaliparamba WS Dn EE
08 Jan 2024 103.06 km PVC Layed,75 number FHTC provided Thaliparamba WS Dn EE
05 Jan 2024 100.96 km PVC Layed,56 number FHTC provided Thaliparamba WS Dn EE
03 Jan 2024 100.52 km PVC Layed,56 number FHTC provided Thaliparamba WS Dn EE
01 Jan 2024 95.74 km PVC Layed,35 number FHTC provided Thaliparamba WS Dn EE
28 Dec 2023 95.74 km PVC Layed,35 number FHTC provided Thaliparamba WS Dn EE
26 Dec 2023 95.74 km PVC Layed,35 number FHTC provided Thaliparamba WS Dn EE