Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Apr 2024 112.48km PVC Layed, 159 number FHTC provided. Thaliparamba WS Dn EE
19 Apr 2024 112.48km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
17 Apr 2024 112.38km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
15 Apr 2024 112.27km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
11 Apr 2024 112.21km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
08 Apr 2024 112.15 km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
05 Apr 2024 112.11 km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
02 Apr 2024 112.11 km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
30 Mar 2024 112.11 km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE
27 Mar 2024 112.11 km PVC Layed, 159 number FHTC provided Thaliparamba WS Dn EE