Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Apr 2024 | 112.48km PVC Layed, 159 number FHTC provided. | Thaliparamba WS Dn EE | |
19 Apr 2024 | 112.48km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
17 Apr 2024 | 112.38km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
15 Apr 2024 | 112.27km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
11 Apr 2024 | 112.21km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
08 Apr 2024 | 112.15 km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
05 Apr 2024 | 112.11 km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
02 Apr 2024 | 112.11 km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
30 Mar 2024 | 112.11 km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE | |
27 Mar 2024 | 112.11 km PVC Layed, 159 number FHTC provided | Thaliparamba WS Dn EE |