23 May 2024 112.48km PVC/DI Layed, 159 number HTC provided. Thaliparamba WS Dn EE
20 May 2024 112.48km PVC/DI Layed, 159 number HTC provided. Thaliparamba WS Dn EE
18 May 2024 112.48km PVC/DI Layed, 159 number HTC provided. Thaliparamba WS Dn EE
13 May 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
10 May 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
06 May 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
02 May 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
29 Apr 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
25 Apr 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE
23 Apr 2024 112.48km PVC Layed, 159 number HTC provided. Thaliparamba WS Dn EE