| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Feb 2023 | An agreement signed with Mr. Bobby kuriyan | Kattappana AEE 1 | |
| 20 Feb 2023 | An agreement signed with Mr. Bobby kuriyan, Expecting to start the job by 20/2/23 | Kattappana AEE 1 | |
| 16 Feb 2023 | An agreement signed with Mr. Bobby kuriyan, Expecting to start the job by 20/2/23 | Kattappana AEE 1 | |
| 15 Feb 2023 | An agreement signed with Mr. Bobby kuriyan, Expecting to start the job by 20/2/23 | Kattappana AEE 1 | |
| 14 Feb 2023 | An agreement signed, Expecting to start the job by 20/2/23 | Kattappana AEE 1 | |
| 10 Feb 2023 | An agreement signed, Expecting to start the job by 20/2/23 | Kattappana AEE 1 | |
| 10 Feb 2023 | Work order issued | Kattappana AEE 1 | |
| 07 Feb 2023 | Work order issued | Kattappana AEE 1 | |
| 06 Feb 2023 | Work order issued | Kattappana AEE 1 | |
| 04 Feb 2023 | Tender opened work order issued | Kattappana AEE 1 |