| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Apr 2023 | Waiting for KRFB to start the road work. | Kattappana AEE 1 | |
| 01 Apr 2023 | Waiting for KRFB to start the road work. | Kattapana AE 1 | |
| 29 Mar 2023 | Site handover was done on 22/01/2023. The pipe reached the site. | Kattappana AEE 1 | |
| 26 Mar 2023 | Pipe dispatched from company | Kattappana AEE 1 | |
| 23 Mar 2023 | Pipe dispatched from company | Kattappana AEE 1 | |
| 22 Mar 2023 | Pipe dispatched from company | Kattapana AE 1 | |
| 21 Mar 2023 | DI Pipe submitted for testing, Waiting for test results. | Kattappana AEE 1 | |
| 20 Mar 2023 | DI Pipe submitted for testing, Waiting for test results. | Kattappana AEE 1 | |
| 17 Mar 2023 | DI Pipe submitted for testing, Waiting for test results. | Kattappana AEE 1 | |