| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Jun 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattapana AE 1 | |
| 03 Jun 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattappana AEE 1 | |
| 01 Jun 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattapana AE 1 | |
| 29 May 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattapana AE 1 | |
| 25 May 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattappana AEE 1 | |
| 22 May 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattappana AEE 1 | |
| 18 May 2023 | Waiting for KRFB to start the road work.Pipes arrived at site. | Kattapana AE 1 | |
| 15 May 2023 | Waiting for KRFB to start the road work. | Kattappana AEE 1 | |
| 12 May 2023 | Waiting for KRFB to start the road work. | Kattapana AE 1 | |
| 09 May 2023 | Waiting for KRFB to start the road work. | Kattapana AE 1 |