JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs

Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs
Project Code KNRJJM09218683
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying gravity main , Construction of service reservoirs (8 LL, 1.5LL,1LL,0.25LL) ,laying pumping mains, laying distribution system and providing 4289 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
AS Amount (Rs) 532000000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 528400000
TS Number 17862/2021-2022
Total Bill Submitted (Rs) 96455184
Total Bill Paid (Rs) 23138517
Population Benefitted 26823
Capacity in MLD 42.00
Actual Project Completion Date 31 Aug 2024
Coverage 5139 nos FHTCs.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -I Mattannur Project Dn
2 JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III Mattannur Project Dn
3 JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYTH-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs- Zone-II Mattannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Oct 2024 Earth Excavation and Pipe laying is in progress Mattannur Project Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/09/2023
Scheduled date of Completion of the Project 30 Sep 2024
Expected date of Completion 31/12/2025

Processing Dates

AS Date 18 Sep 2021
TS Date 13 Jan 2022

Other details

Project Officers View