JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYTH-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs- Zone-II

Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYTH-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs- Zone-II
Project Code KNRJJM09218683P3
Type Package
Main Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 1.5 LL OHSR at Chithramala ,Laying of Pumping main,Supply and Errection of Pump sets,Distribution system and Providing 600nos FHTCs.
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 60000000
TS Number 10347/2023-2024
Technical specification Construction of 1.5 LL OHSR,Laying of Pumping main,Supply and Errection of Pump sets,Distribution system and Providing 600nos FHTCs.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/09/2023
Scheduled date of Completion as per agreement 30 Apr 2024
Expected date of Completion 31/05/2025

Processing Dates

TS Date 28 Jul 2023
Estimate Approval 28 Jul 2023
NIT Approval 05 Aug 2023
Tender Closing 18 Aug 2023
Technichal Pre-Qualification 05 Aug 2023
Price bid opening 19 Aug 2023

Approval Dates

Workorder Date 30 Sep 2023
NA 25 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 76% Completed

Earth excavation and Pipe laying is in progress. Total distribution is 19.88 km. Pipe supplied is 19.88 km. Out of this 19.5 km pipe laid completed. Construction of 1.5 LL OHSR at CHITHRAMALA completed, plastering also completed. DI of size 100 mm Distribution main , 90mm 10kg completed. 50mm 12.5kg PVC distribution laying work in progress at Malur city-Karumundayad -Kavinmoola Road. House connection work also in progress 300 nos. completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 75% Completed

Earth excavation and Pipe laying is in progress. Total distribution is 19.88 km. Pipe supplied is 19.88 km. Out of this 19.5 km pipe laid completed. Construction of 1.5 LL OHSR at CHITHRAMALA completed, plastering also completed. DI of size 100 mm Distribution main , 90mm 10kg completed. 50mm 12.5kg PVC distribution laying work in progress at Malur city-Karumundayad -Kavinmoola Road. House connection work also in progress, 250 nos. completed.