Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYTH-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs- Zone-II |
---|---|
Project Code | KNRJJM09218683P3 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 1.5 LL OHSR at Chithramala ,Laying of Pumping main,Supply and Errection of Pump sets,Distribution system and Providing 600nos FHTCs. |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 60000000 |
TS Number | 10347/2023-2024 |
Technical specification | Construction of 1.5 LL OHSR,Laying of Pumping main,Supply and Errection of Pump sets,Distribution system and Providing 600nos FHTCs. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/09/2023 |
---|---|
Scheduled date of Completion as per agreement | 30 Apr 2024 |
Expected date of Completion | 31/05/2025 |
TS Date | 28 Jul 2023 |
---|---|
Estimate Approval | 28 Jul 2023 |
NIT Approval | 05 Aug 2023 |
Tender Closing | 18 Aug 2023 |
Technichal Pre-Qualification | 05 Aug 2023 |
Price bid opening | 19 Aug 2023 |
Workorder Date | 30 Sep 2023 |
---|---|
NA | 25 Sep 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 76% Completed
Earth excavation and Pipe laying is in progress. Total distribution is 19.88 km. Pipe supplied is 19.88 km. Out of this 19.5 km pipe laid completed. Construction of 1.5 LL OHSR at CHITHRAMALA completed, plastering also completed. DI of size 100 mm Distribution main , 90mm 10kg completed. 50mm 12.5kg PVC distribution laying work in progress at Malur city-Karumundayad -Kavinmoola Road. House connection work also in progress 300 nos. completed.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 75% Completed
Earth excavation and Pipe laying is in progress. Total distribution is 19.88 km. Pipe supplied is 19.88 km. Out of this 19.5 km pipe laid completed. Construction of 1.5 LL OHSR at CHITHRAMALA completed, plastering also completed. DI of size 100 mm Distribution main , 90mm 10kg completed. 50mm 12.5kg PVC distribution laying work in progress at Malur city-Karumundayad -Kavinmoola Road. House connection work also in progress, 250 nos. completed.