JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -I

Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -I
Project Code KNRJJM09218683P1
Type Package
Main Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description common gravity main is proposed from WTP, ( KIIFB WSS to Mattanur and Iritty Municipalities) using 350mm & 300mm DI K9 Pipe for Chithrapeetam (8 LL GLSR) ,Pumping main,distribution system and providing 4289nos. FHTCs.
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 528400000
TS Number 17862/2021-2022
Technical specification common gravity main is proposed from WTP, ( KIIFB WSS to Mattanur and Iritty Municipalities) using 350mm & 300mm DI K9 pipes to the proposed 8 LL GLSR at Chithrapeetam. Construction of Service Reservoirs 8 LL GLSR, distribution system to the 85% area of Malur panchayat and providing 4289nos. FHTCs.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/09/2023
Scheduled date of Completion as per agreement 11 Sep 2024
Expected date of Completion 31/12/2025

Processing Dates

TS Date 13 Jan 2022
Estimate Approval 13 Jan 2022
NIT Approval 02 Dec 2022
Tender Closing 17 Apr 2023
Technichal Pre-Qualification 02 Dec 2022
Price bid opening 19 Apr 2023

Approval Dates

Workorder Date 08 Aug 2023
NA 04 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 40% Completed

Earth excavation and Pipe laying is on progress. Total distribution is 206.303 km, in that 104.104 km pipe has supplied, Out of this 83 km pipe laying competed. Common gravity DI of size 350mm for THILLENKERY&MALUR GP from WTP to storage reservior up to Naduvanad (4.90KM ) completed.300mm DI laying upto Karothuvayal is under process. House connection work is in progress. 251nos. HTC completed. Construction of 8LL GLSR Earth leveling work initial stage completed at Karothuvayal.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 40% Completed

Earth excavation and Pipe laying is on progress. Total distribution is 206.303 km, in that 104.104 km pipe has supplied, Out of this 83 km pipe laying competed. Common gravity DI of size 350mm for THILLENKERY&MALUR GP from WTP to storage reservior up to Naduvanad (4.90KM ) completed.300mm DI laying upto Karothuvayal is under process. House connection work is in progress. 251nos. HTC completed. Construction of 8LL GLSR Earth leveling work initial stage completed at Karothuvayal.