Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III |
---|---|
Project Code | KNRJJM09218683P2 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 39800000 |
TS Number | 9090/2023-2024 |
Technical specification | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 19 Jul 2024 |
Expected date of Completion | 31/03/2025 |
TS Date | 16 Jul 2023 |
---|---|
Estimate Approval | 16 Jul 2023 |
NIT Approval | 22 Jul 2023 |
Tender Closing | 18 Aug 2023 |
Technichal Pre-Qualification | 25 Jul 2023 |
Price bid opening | 19 Aug 2023 |
Workorder Date | 27 Sep 2023 |
---|---|
NA | 10 Oct 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 5% Completed
Earth excavation and Pipe laying is in progress. Total distribution 18.5 km,pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed. 1 LL Capacity OHSR site at Palukachippara earth leveling work is awaiting. 0.25 LL sump at Padaupara earth leveling work initial stage completed.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 5% Completed
Earth excavation and Pipe laying is in progress. Total distribution 18.5 km,pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed. 1 LL Capacity OHSR site at Palukachippara earth leveling work is awaiting. 0.25 LL sump at Padaupara earth leveling work initial stage completed.