JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III

Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III
Project Code KNRJJM09218683P2
Type Package
Main Project JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 39800000
TS Number 9090/2023-2024
Technical specification Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/10/2023
Scheduled date of Completion as per agreement 19 Jul 2024
Expected date of Completion 31/03/2025

Processing Dates

TS Date 16 Jul 2023
Estimate Approval 16 Jul 2023
NIT Approval 22 Jul 2023
Tender Closing 18 Aug 2023
Technichal Pre-Qualification 25 Jul 2023
Price bid opening 19 Aug 2023

Approval Dates

Workorder Date 27 Sep 2023
NA 10 Oct 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 5% Completed

Earth excavation and Pipe laying is in progress. Total distribution 18.5 km,pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed. 1 LL Capacity OHSR site at Palukachippara earth leveling work is awaiting. 0.25 LL sump at Padaupara earth leveling work initial stage completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 5% Completed

Earth excavation and Pipe laying is in progress. Total distribution 18.5 km,pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed. 1 LL Capacity OHSR site at Palukachippara earth leveling work is awaiting. 0.25 LL sump at Padaupara earth leveling work initial stage completed.