| Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III |
|---|---|
| Project Code | KNRJJM09218683P2 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 39800000 |
| TS Number | 9090/2023-2024 |
| Technical specification | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
| Contractor | K.K.SURENDRAN (Mob: 9447038315) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 19 Jul 2024 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 16 Jul 2023 |
|---|---|
| Estimate Approval | 16 Jul 2023 |
| NIT Approval | 22 Jul 2023 |
| Tender Closing | 18 Aug 2023 |
| Technichal Pre-Qualification | 25 Jul 2023 |
| Price bid opening | 19 Aug 2023 |
| Workorder Date | 27 Sep 2023 |
|---|---|
| NA | 10 Oct 2023 |
| Mattannur Project Sn 2 AE |
| Date: 22/04/2026 |
Work in progress | 6% Completed
Total distribution 18.5 km, Pipe supplied is 18.5 km. out of this supply 2.5 km pipe laying completed.Proposed land for the construction of sump(0.25LL) at padupara is not feasible to KWA,another location has to be find by panchayath,it will be discussed with panchayath authority. 1LL capacity OHSR at Palukachipara not started.BSNL road cutting permission to lay pumping main from padupara to palukachipara not obtained. Letter submitted to BSNL regarding this issue and AE directly contacted the BSNL AGM Office Kannur.
| Mattannur Project Sn 2 AE |
| Date: 08/04/2026 |
Work in progress | 6% Completed
Total distribution 18.5 km, Pipe supplied is 18.5 km. out of this supply 2km pipe laid completed.Proposed land for the construction of sump(0.25LL) at padupara is not feasible to KWA,another location has to be find by panchayath,it will be discussed with panchayath authority. 1LL capacity OHSR at Palukachipara not started.BSNL road cutting permission to lay pumping main from padupara to palukachipara not obtained. Letter submitted to BSNL regarding this issue and AE directly contacted the BSNL AGM Office Kannur.