| Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs-Zone -III |
|---|---|
| Project Code | KNRJJM09218683P2 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT-MALUR GRAMA PANCHAYAT-WSS TO MATTANNUR & IRITTY AND ADJOINING PANCHAYATH PHASE III- Laying Distribution System and Providing FHTCs |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 39800000 |
| TS Number | 9090/2023-2024 |
| Technical specification | Construction of 0.25 LL sump cum pump house at Padupara, Construction of 1 LL OHSR at Palukachipara, Pumping main, Laying Distribution system and providing 250 Nos FHTCs |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 19 Jul 2024 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 16 Jul 2023 |
|---|---|
| Estimate Approval | 16 Jul 2023 |
| NIT Approval | 22 Jul 2023 |
| Tender Closing | 18 Aug 2023 |
| Technichal Pre-Qualification | 25 Jul 2023 |
| Price bid opening | 19 Aug 2023 |
| Workorder Date | 27 Sep 2023 |
|---|---|
| NA | 10 Oct 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 6% Completed
Earth excavation and Pipe laying is in progress. Total distribution 18.5 km, Pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed..
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 6% Completed
Earth excavation and Pipe laying is in progress. Total distribution 18.5 km, Pipe supplied is 18.5 km. out of this supply 1.5 km pipe laid completed..