Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-WSS to Amballoor, Edakkattuvayal, Maneed, Mulamthuruthy panchayaths in Ernakulam District - Providing FHTCs in all Households

Project JJM-WSS to Amballoor, Edakkattuvayal, Maneed, Mulamthuruthy panchayaths in Ernakulam District - Providing FHTCs in all Households
Project Code EKMJJM092111040
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-WSS to Amballoor, Edakkattuvayal, Maneed, Mulamthuruthy panchayaths in Ernakulam District
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
AS Amount (Rs) 1184600000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 918604000
TS Number WRD/KWA-CE(CR)/EST_ TS/11477/2022_5_2_1
Total Bill Submitted (Rs) 16930191
Total Bill Paid (Rs) 16930191
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM-WSS to Maneedu, Mulamthuruthy, Edakkattuvayal and Amballoor Panchayaths in Ernakulam District-Part - I - Design and construction of Production components,OHSR 9LL capacity at WTP site and providing pump sets & allied works-General Civil Work Project Division Perumbavoor
2 JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths in Ernakulam District - part - II - Construction of 5 nos OHSR's, Laying CWPM & GM , Laying Distribution lines to all zones and providing FHTC - general civil work. Project Division Piravom(Kattapana)
3 JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths. Laying of gravity main and distribution lines to be laid along Arakkunnam - Ambaloor & Poothotta - Piravom KSTP roads in Edakkattuvayal and Amballoor Panchayath area Project Division Piravom(Kattapana)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 PART II - Laying of 90 mm & 160 mm pvc pipes in progress.Arayankavu tank excavation work ongoing. KSTP ROAD - 80% FHTC given work in progress.PART-I-work tendered Piravom Project Dn AE 1
07 Sep 2023 PART II - PVC & GI pipes will be delivered by 1st week of September. DI pipes will be delivered in 30-45 days after receipt of the CIPET call letter. KSTP ROAD - 74% FHTC given work in progress.PART-I-work tendered Piravom Project Dn AE 1
24 Aug 2023 PART II - PVC & GI pipes will be delivered by 1st week of September. DI pipes will be delivered in 30-45 days after receipt of the CIPET call letter. KSTP ROAD - 74% FHTC given work in progress.69 FHTC given Piravom Project Dn AE 1
17 Aug 2023 PART II-Field survey ongoing. KSTP ROAD- 74% FHTC given work in progess . 69 FHTC given Piravom Project Dn AE 1
11 Aug 2023 PART II-Field survey ongoing. KSTP ROAD- 72% work in progress Piravom Project Dn AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 18 Sep 2021
TS Date 06 Jan 2023

Other details

Project Officers View