Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths in Ernakulam District - part - II - Construction of 5 nos OHSR's, Laying CWPM & GM , Laying Distribution lines to all zones and providing FHTC - general civil work.

Project JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths in Ernakulam District - part - II - Construction of 5 nos OHSR's, Laying CWPM & GM , Laying Distribution lines to all zones and providing FHTC - general civil work.
Project Code EKMJJM092111040P2
Type Package
Main Project JJM-WSS to Amballoor, Edakkattuvayal, Maneed, Mulamthuruthy panchayaths in Ernakulam District - Providing FHTCs in all Households
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths in Ernakulam District - part - II - Construction of 5 nos OHSR's, Laying CWPM & GM , Laying Distribution lines to all zones and providing FHTC - general civil work.
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 918604000
TS Number WRD/KWA-CE(CR)/EST_ TS/11477/2022_5_2_1
Technical specification Name and address of contractor:M/s Strafa Projects Pvt Ltd , Plot No-34,Eswaraiah Enclave,Dammaiguda ,Hyderabad 500083

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/09/2021
Scheduled date of Completion as per agreement 23 Mar 2024
Expected date of Completion 23/03/2024

Processing Dates

TS Date 06 Jan 2023
Estimate Approval 05 Jan 2023
NIT Approval 01 Feb 2023
Tender Closing 20 Feb 2023
Price bid opening 15 Feb 2023

Approval Dates

Workorder Date 24 Mar 2023
NA 26 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravom Project Dn AE 1
Date: 17/05/2024

Work in progress | 22% Completed

Laying of 90 mm,110 mm,140 mm & 160 mm pvc pipes &350 mm DI pumping main laying in progress.At Maneed panchayath- 1.225 km raw water pumping main & 3.5 km distribution line completed,mulanthuruthy panchayath-2.5 km distribution laying completed,Edakkattuvayal panchayath- 6 km distribution pipe laying completed,Amballoor panchayath-8 km distribution pipe laying completed. Arayankavu tank- column first stage completed and veliyanad tank column concrete completed. Kanjiramattom tank site plinth beam completed. Thottapady tank site pedestal columns completed.148 connections given at amballoor panchayath,100 connections given at edakkuttuvayal panchayath and 2 connections given at mulanthuruthy panchayath..

Piravom Project Dn AE 1
Date: 14/05/2024

Work in progress | 22% Completed

Laying of 90 mm,110 mm,140 mm & 160 mm pvc pipes &350 mm DI pumping main laying in progress.At Maneed panchayath- 1.225 km raw water pumping main & 3.5 km distribution line completed,mulanthuruthy panchayath-2.5 km distribution laying completed,Edakkattuvayal panchayath- 6 km distribution pipe laying completed,Amballoor panchayath-8 km distribution pipe laying completed. Arayankavu tank- column first stage completed and veliyanad tank column concrete completed. Kanjiramattom tank site plinth beam completed. Thottapady tank site pedestal columns completed..