Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2023 | PART II - Laying of 90 mm & 160 mm pvc pipes in progress.Arayankavu tank excavation work ongoing. KSTP ROAD - 80% FHTC given work in progress.PART-I-work tendered | Piravom Project Dn AE 1 | |
07 Sep 2023 | PART II - PVC & GI pipes will be delivered by 1st week of September. DI pipes will be delivered in 30-45 days after receipt of the CIPET call letter. KSTP ROAD - 74% FHTC given work in progress.PART-I-work tendered | Piravom Project Dn AE 1 | |
24 Aug 2023 | PART II - PVC & GI pipes will be delivered by 1st week of September. DI pipes will be delivered in 30-45 days after receipt of the CIPET call letter. KSTP ROAD - 74% FHTC given work in progress.69 FHTC given | Piravom Project Dn AE 1 | |
17 Aug 2023 | PART II-Field survey ongoing. KSTP ROAD- 74% FHTC given work in progess . 69 FHTC given | Piravom Project Dn AE 1 | |
11 Aug 2023 | PART II-Field survey ongoing. KSTP ROAD- 72% work in progress | Piravom Project Dn AE 1 | |
04 Aug 2023 | PART II-Field survey ongoing. KSTP ROAD- 72% work in progress | Piravom Project Dn AE 1 | |
29 Jul 2023 | PART II-Field survey ongoing. KSTP ROAD- 72% work in progress | Piravom Project Dn AE 1 | |
18 Jul 2023 | Part-II -site cleaning works and design of OHSR in progress. ,manned KSTP - FHTC given work in progress. | Piravom Project Dn AE 1 | |
06 Jul 2023 | part II -agreement executed, maneed KSTP-72% | Piravom Project Dn AE 1 | |
30 Jun 2023 | AGREEMENT ISSUED | Piravom Project Dn AE 1 |