JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths. Laying of gravity main and distribution lines to be laid along Arakkunnam - Ambaloor & Poothotta - Piravom KSTP roads in Edakkattuvayal and Amballoor Panchayath area

Project JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths. Laying of gravity main and distribution lines to be laid along Arakkunnam - Ambaloor & Poothotta - Piravom KSTP roads in Edakkattuvayal and Amballoor Panchayath area
Project Code EKMJJM092111040P1
Type Package
Main Project JJM-WSS to Amballoor, Edakkattuvayal, Maneed, Mulamthuruthy panchayaths in Ernakulam District - Providing FHTCs in all Households
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-WSS to Maneed, Mulanthuruthy, Edakkattuvayal and Amballoor panchayaths. Laying of gravity main and distribution lines to be laid along Arakkunnam - Ambaloor & Poothotta - Piravom KSTP roads in Edakkattuvayal and Amballoor Panchayath area.
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 33800000
TS Number TS/2022-2023/2022/27355
Technical specification Supply & Laying of 300 mm DI K9 pipe - 1949 M, 200 mm DI K9 pipe - 2029 M & 160 mm PVC pipe 10 kg/cm2 - 2778 M
Contractor M/s.Lurdhmatha Constructions (Mob: 9497685037)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/09/2022
Scheduled date of Completion as per agreement 30 Apr 2023
Expected date of Completion 30/04/2023

Processing Dates

TS Date 15 Jul 2022
Estimate Approval 15 Jul 2022
NIT Approval 15 Jul 2022
Tender Closing 15 Jul 2022
Price bid opening 11 Jul 2022

Approval Dates

Workorder Date 02 Sep 2022
NA 15 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravom Project Dn AE 1
Date: 17/05/2024

Work in progress | 95% Completed

200 mm DI pipe laying in progress. 160 mm pvc -2499 m completed,200 DI-1891.9 M, 300 DI gravity main- 1910.9 m. 188 nos FHTC given. .

Piravom Project Dn AE 1
Date: 14/05/2024

Work in progress | 95% Completed

200 mm DI pipe laying in progress. 160 mm pvc -2499 m completed,200 DI-1891.9 M, 300 DI gravity main- 1910.9 m. 188 nos FHTC given..