NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II
| Project |
NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II |
| Project Code |
PTANABARD1118603 |
| Type |
Main project |
| Category |
NABARD |
| Description |
Laying distribution sysytem in Niranam & kadapra (Part )Pts. |
| District |
Pathanamthitta |
| Execution |
Adoor Project Dn |
| AS Amount (Rs) |
200000000.00 |
| Total Bill Submitted (Rs) |
111911000.00 |
| Total Bill Paid (Rs) |
26900000.00 |
| Coverage |
Niranam & kadapra (Part )Pts |
| Implementation Schedule |
View Schedule Chart |
| Work Plan |
Download |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 04 May 2021 |
105 km pipeline completed |
Adoor Project Dn EE |
|
| 14 Apr 2021 |
98 KM COMPLETED |
Adoor Project Dn EE |
|
| 31 Mar 2021 |
Charging in Panachimudu junction in progress |
Adoor Project Dn EE |
|
| 26 Mar 2021 |
Pipe laying in progress |
Adoor Project Dn EE |
|
| 24 Mar 2021 |
Vadkkumbhagam area CHARGED |
Adoor Project Dn EE |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 10 Mar 2021 |
Pending |
Pending |
Project Risks related to road cutting sanction from PWD/NH |
No comments available. |
Pending |
| 12 Aug 2020 |
Pending |
22 Feb 2021 |
Clearance from other department |
Assistant executive engineer( bRIDGES thiruvalla ) submitted the report to EE. Sanction for laying pipe line to be obtained obtained from EE BRIDGES Alappuzha |
Action Taken |
| 03 Feb 2020 |
Pending |
02 Feb 2021 |
Road cutting estimate to be obtained from Roads division Alappuzha |
Joint inspection completed. Estimate to be obtained |
Action Taken |
| 03 Dec 2019 |
31 Dec 2019 |
17 Nov 2020 |
Project Risks related to road cutting sanction from PWD/NH |
Work in progress |
Solved |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II |
Adoor Project Dn |
|
Duration & Sanction dates
| Date of Sanction |
07/11/2018 |
| Date of start |
10/01/2020 |
| Expected date of Completion |
31/03/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
NABARD |
Processing Dates
| AS Date |
07 Nov 2018 |
| TS Date |
06 Mar 2019 |
| Estimate Approval |
06 Mar 2019 |
| Supplying and Laying |
20 Dec 2019 |
Approval Dates
| Workorder Date |
20 Sep 2019 |
| Agreement Date |
24 Oct 2019 |