NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II
Project |
NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II |
Project Code |
PTANABARD1118603 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Laying distribution sysytem in Niranam & kadapra (Part )Pts. |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Adoor Project Dn |
AS Amount (Rs) |
200000000
|
AS Number |
GO.(Rt.)No. 799/2018/WRD |
TS Amount (Rs) |
200000000 |
TS Number |
TS/2018-2019/2018/2590 |
Total Bill Submitted (Rs) |
162516144 |
Total Bill Paid (Rs) |
151194665 |
Population Benefitted |
34272 |
Capacity in MLD |
14.00 |
Actual Project Completion Date |
31 May 2022 |
Coverage |
Niranam & kadapra (Part )Pts |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Package 2 - 350 MM MS FABRICATION FOR BRIDGE CROSSING IN KADAPRA PANCHAYATH |
Adoor Project Dn |
|
2 |
Package 4 -NABARD RIDFXXIV- CRWSS TO NEDUMBRAM NIRANAM,KADAPRA,PERINGARA PANCHAYATHS- Replacement of 15/5A CT&PT and TOD Meter of unitized substation WTP Pulikkezhu. |
Adoor Project Dn |
|
3 |
Package I -CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II |
Adoor Project Dn |
|
4 |
Package III - NABARD RIDFXXIV- CRWSS TO NEDUMBRAM NIRANAM,KADAPRA,PERINGARA PANCHAYATHS- ALTRATION OF HOUSE CONNECTION |
Adoor Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Mar 2023 |
CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 2.07 crores upto 1/2023 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. |
Adoor Project Dn EE |
|
30 Aug 2022 |
CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. |
Adoor Project Dn AE3 |
|
18 Jul 2022 |
CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. |
Adoor Project Dn AE3 |
|
10 Jul 2022 |
CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity |
Adoor Project Dn AE3 |
|
08 Jul 2022 |
CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity |
Adoor Project Dn AE3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/01/2020 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
15/08/2023 |
Processing Dates
AS Date |
07 Nov 2018 |
TS Date |
06 Mar 2019 |