Package 2 - 350 MM MS FABRICATION FOR BRIDGE CROSSING IN KADAPRA PANCHAYATH

Project Package 2 - 350 MM MS FABRICATION FOR BRIDGE CROSSING IN KADAPRA PANCHAYATH
Project Code PTANABARD1118603P2
Type Package
Main Project NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description This work includes 350 MM MS FABRICATION FOR BRIDGE CROSSING IN Parumala & Pannayikkadavu bridges.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 3980000
TS Number TS/2021-22/2021/8341
Technical specification This work includes 350 MM MS FABRICATION FOR BRIDGE CROSSING IN Parumala & Pannayikkadavu bridges.
Contractor Biju Augustine (Mob: 9447060360)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
15 Jul 2020 Pending Pending Social Project Risks Permission for laying distribution main from Pannayikkadavu bridge to Parumala bridge is to be obtained from PWD Roads division Alappuzha No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/07/2021
Scheduled date of Completion as per agreement 11 Sep 2021
Expected date of Completion 11/09/2021

Processing Dates

TS Date 23 Apr 2021
Estimate Approval 23 Apr 2021
NIT Approval 23 Apr 2021
Tender Closing 24 May 2021
Technichal Pre-Qualification 26 May 2021
Price bid opening 26 May 2021

Approval Dates

NA 12 Jul 2021
Workorder Date 12 Jul 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Adoor Project Dn AE3
Date: 07/10/2021

Work has been completed | 100% Completed

MS fabrication work completed & line charged .

Adoor Project Dn AE3
Date: 06/10/2021

Work has been completed | 100% Completed

MS fabrication work completed & line charged .