| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Mar 2023 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 2.07 crores upto 1/2023 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn EE | |
| 30 Aug 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn AE3 | |
| 18 Jul 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn AE3 | |
| 10 Jul 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity | Adoor Project Dn AE3 | |
| 08 Jul 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity | Adoor Project Dn AE3 | |
| 28 Jun 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity | Adoor Project Dn EE | |
| 18 Jun 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn EE | |
| 14 Jun 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn AE3 | |
| 10 Jun 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn AE3 | |
| 01 Jun 2022 | CT PT and TOD meter supplied. KSEB is insisting for clearing arrears of 1.25 crores upto 2/2022 in addition to addln security deposit of 13 lakhs. Request submitted to KSEB for sanction without paying pending arrears. DCE KSEB informed that the decision can be taken at higher level only and has submitted proposal to CE KSEB. Higher level intervention required as addln 82 kW motors are idling resulting in reduced production capacity. | Adoor Project Dn AE3 |