Package III - NABARD RIDFXXIV- CRWSS TO NEDUMBRAM NIRANAM,KADAPRA,PERINGARA PANCHAYATHS- ALTRATION OF HOUSE CONNECTION
| Project |
Package III - NABARD RIDFXXIV- CRWSS TO NEDUMBRAM NIRANAM,KADAPRA,PERINGARA PANCHAYATHS- ALTRATION OF HOUSE CONNECTION |
| Project Code |
PTANABARD1118603P3 |
| Type |
Package |
| Main Project |
NABARD-RIDF-XXIV-CRWSS to Nedumpuram, Niranam, Kadapra and Peringara panchayat in Pathanamthitta district Phase II
|
| Funding Agency |
NABARD |
| Category |
NABARD |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-98 (01) |
| Description |
THIS WORK INCLUDES ALTRATION OF HOUSE CONNECTIONS TO NEWLY LAID LINE |
| Status |
On-going |
| District |
Pathanamthitta |
| Executing Office |
Adoor Project Dn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
16451000 |
| TS Number |
TS/2021-2022/2020/28762 |
| Technical specification |
THIS WORK INCLUDES ALTRATION OF 3500 HOUSE CONNECTIONS TO NEWLY LAID LINE |
| Contractor |
Biju Augustine (Mob: 9447060360) |
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 30 Sep 2021 |
20 Dec 2022 |
Pending |
Natural Calamities Related |
House connection altration cannot be done due to water seepage & water logging |
Water levl receded and work restarted |
Solved |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
19/04/2021 |
| Scheduled date of Completion as per agreement |
31 Mar 2022 |
| Expected date of Completion |
31/03/2022 |
Processing Dates
| TS Date |
19 Apr 2021 |
| Estimate Approval |
19 Apr 2021 |
| NIT Approval |
19 Apr 2021 |
| Tender Closing |
03 May 2021 |
| Technichal Pre-Qualification |
05 May 2021 |
| Price bid opening |
05 May 2021 |
Approval Dates
| Workorder Date |
25 Jun 2021 |
| NA |
07 Jul 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Adoor Project Dn EE |
| Date: 31/03/2022 |
Work has been completed | 100% Completed
Completed.
| Adoor Project Dn AE3 |
| Date: 30/03/2022 |
Work in progress | 84% Completed
2128 connections completed.