Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA

Project AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Project Code KNRAMRUT112213592
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Status On-going
District Kannur
Executing Office Thaliparambu WS Dn
AS Amount (Rs) 69140000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 50900000
TS Number 14916/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work Thaliparamba WS Sn
2 AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work Thaliparamba WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2025 1 LL OHSR structure work completed, plasteringcompleted . Connection work completed 926 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work pending Thaliparamba WS Sub Dn
19 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
14 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
13 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
12 Feb 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/06/2023
Scheduled date of Completion of the Project 12 Mar 2024
Expected date of Completion 31/08/2025

Processing Dates

AS Date 24 Nov 2022
TS Date 27 Feb 2023

Other details

Project Officers View