AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work

Project AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work
Project Code KNRAMRUT112213592P1
Type Package
Main Project AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0 -TALIPARAMBA MUNCIPALITY -PACKAGE - I -CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs -General Civil Work
Status On-going
District Kannur
Executing Office Thaliparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 50900000
TS Number WRD/KWA-CE(NR)/EST_TS/16934/2022_5_1_1
Technical specification CONSTRUCTION OF 1.00 LL OHSR AT PULIMPARAMBA, SUPPLYING & LAYING DISTRIBUTION NET WORK AND PROVIDING FHTCs.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/06/2023
Scheduled date of Completion as per agreement 12 Mar 2024
Expected date of Completion 12/09/2024

Processing Dates

TS Date 27 Feb 2023
Estimate Approval 27 Feb 2023
NIT Approval 08 Mar 2023
Tender Closing 30 Mar 2023
Technichal Pre-Qualification 11 May 2023
Price bid opening 11 Apr 2023

Approval Dates

Workorder Date 18 May 2023
NA 30 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 89% Completed

NH crossing at Keezhatoor vayal by using 150 mm MS Pipeline work started.

Thaliparamba WS Section
Date: 30/04/2025

Work in progress | 85% Completed

1 LL OHSR plastering work completed and painting work in progress . 996 FHTCs Completed. 10km pipes laid out of 12km. Pipe laying in PWD road completed. inter connection work from 800mm DI pipe not started. New NH crossing at Keezhatoor vayal not started..