AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work

Project AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work
Project Code KNRAMRUT112213592P2
Type Package
Main Project AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work.
Status On-going
District Kannur
Executing Office Thaliparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 13210000
TS Number WRD/KWA-CE(NR)/EST_TS/17165/2022_5_1_1
Technical specification Construction of 1LL OHSR at Pushpagiri Laying distribution pipe line.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/07/2024
Scheduled date of Completion as per agreement 29 Jan 2025
Expected date of Completion 31/07/2025

Processing Dates

TS Date 02 Mar 2024
Estimate Approval 02 Mar 2024
NIT Approval 02 Mar 2024
Tender Closing 14 Mar 2024
Technichal Pre-Qualification 19 Mar 2024
Price bid opening 15 Mar 2024

Approval Dates

Workorder Date 16 Mar 2024
NA 26 Jul 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Sub Dn
Date: 27/06/2025

Work in progress | 90% Completed

Interconnection work with 900mm DI pipe pending. Finishing works pending .

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 85% Completed

Road restoration work completed.