Project | AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work |
---|---|
Project Code | KNRAMRUT112213592P2 |
Type | Package |
Main Project | AMRUT-TALIPARAMBA MUNICIPALITY-AMRUT 2.0-2022-23 - CONSTRUCTION OF OHSRs AT PUSHPAGIRI AND PULIMPARAMBA, LAYING DISTRIBUTION PIPE LINE AND PROVIDING FHTCs IN TALIPARAMBA |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT-Taliparamba Muncipality -AMRUT 2.0 -2022-23-Construction of OHSR at Pushpagiri Laying distribution pipe line-Taliparamba Muncipality -AMRUT 2.0 -2022-23-General Civil Work. |
Status | On-going |
District | Kannur |
Executing Office | Thaliparamba WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 13210000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/17165/2022_5_1_1 |
Technical specification | Construction of 1LL OHSR at Pushpagiri Laying distribution pipe line. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/07/2024 |
---|---|
Scheduled date of Completion as per agreement | 29 Jan 2025 |
Expected date of Completion | 31/07/2025 |
TS Date | 02 Mar 2024 |
---|---|
Estimate Approval | 02 Mar 2024 |
NIT Approval | 02 Mar 2024 |
Tender Closing | 14 Mar 2024 |
Technichal Pre-Qualification | 19 Mar 2024 |
Price bid opening | 15 Mar 2024 |
Workorder Date | 16 Mar 2024 |
---|---|
NA | 26 Jul 2024 |
Thaliparamba WS Sub Dn |
Date: 27/06/2025 |
Work in progress | 90% Completed
Interconnection work with 900mm DI pipe pending. Finishing works pending .
Thaliparamba WS Section |
Date: 19/06/2025 |
Work in progress | 85% Completed
Road restoration work completed.