Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2025 | 1 LL OHSR structure work completed, plasteringcompleted . Connection work completed 926 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work pending | Thaliparamba WS Sub Dn | |
19 Mar 2024 | 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km | Thaliparamba WS Dn EE | |
14 Mar 2024 | 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km | Thaliparamba WS Dn EE | |
13 Mar 2024 | 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km | Thaliparamba WS Dn EE | |
12 Feb 2024 | 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km | Thaliparamba WS Dn EE | |
08 Jan 2024 | 1 LL OHSR covering slab concrete completed , connection work in progress 450 FHTC given out of 996 FHTCs | Thaliparamba WS Dn EE | |
09 Dec 2023 | Tank work Deck slab and haunch concrete completed, side wall concrete completed, connection work in progress 150 FHTCs given | Thaliparamba WS Dn EE | |
30 Nov 2023 | tank work in progress-upto deck slab,connection work going on 100fhtc | Thaliparamba WS Section | |
09 Nov 2023 | Tank construction reached upto deck slab. Pipes supply in progress | Thaliparamba WS Dn EE | |
07 Nov 2023 | work in progress | Thaliparamba WS Section |