Jal Jeevan Mission-Kannur District - Chapparappadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II - Providing FHTCs Thimiri - Vellad Villages

Project Jal Jeevan Mission-Kannur District - Chapparappadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II - Providing FHTCs Thimiri - Vellad Villages
Project Code KNRJJM022213765
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission-Kannur District - Chapparappadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II - Providing FHTCs Thimiri - Vellad Villages
Status On-going
District Kannur
Executing Office Thaliparamba WS Sub Dn
AS Amount (Rs) 617500000
AS Number G.O. 134/2022/WRD
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)- Chapparapadavu - Leak rectification work of Koonam OHSR No.1 for enhancing the quantity of water storage-General Civil Work Thaliparamba WS Sub Dn
2 Jal Jeevan Mission (JJM)-Laying Distribution line & Providing FHTCs -Pipeline Work Thaliparamba WS Sn
3 JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 2.00 LL Sump at Edakkome, Supplying and laying pumping main from Booster station at Edakkome to OHSR at Vilayarkode, Construction of 3.00LL OHSR at Vilayarkode, Supplying and laying transmission main from Vilayarkode to Pakkanhikkad OHSR, Supplying and laying distibution network for Zone-I and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package I Thaliparamba WS Sn
4 JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package II Thaliparamba WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
13 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
09 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
02 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
29 Apr 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/04/2023
Scheduled date of Completion of the Project 31 Mar 2024
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2022

Other details

Project Officers View