Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2025 Shutering of footing of 6L littre Tank Completed. Thaliparamba WS Sub Dn
26 Dec 2024 JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package II Thaliparamba WS Dn EE
18 Jun 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
10 Jun 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
06 Jun 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
03 Jun 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
30 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
23 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
20 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE
17 May 2024 Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing Thaliparamba WS Dn EE