Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2025 | Shutering of footing of 6L littre Tank Completed. | Thaliparamba WS Sub Dn | |
26 Dec 2024 | JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package II | Thaliparamba WS Dn EE | |
18 Jun 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
10 Jun 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
06 Jun 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
03 Jun 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
30 May 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
23 May 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
20 May 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE | |
17 May 2024 | Package-1 Edakkome 2.0 LL sump slab concrete completed. 3LL OHSR base concrete completed.Pipe supply in progress. Package -2 PCC for foundation done for 1 LL OHSR at Pakkanjikkad. Rock blasting progressing at Kattayal for 6 LL OHSR. Pipe supply progressing | Thaliparamba WS Dn EE |