JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package II

Project JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package II
Project Code KNRJJM022213765P2
Type Package
Main Project Jal Jeevan Mission-Kannur District - Chapparappadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II - Providing FHTCs Thimiri - Vellad Villages
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 6.00LL OHSR at Kattayal, Construction of 1.00LL OHSR at Pakkanhikkad, Supplying and laying distibution network for Zone-II and providing FHTCs, LSGD road reformation works and PWD, KSTP, PMGSY road reformation works-Package II
Status On-going
District Kannur
Executing Office Thaliparamba WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 284000000
TS Number 2506/2023-2024
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/10/2023
Scheduled date of Completion as per agreement 30 Oct 2024
Expected date of Completion 31/03/2024

Processing Dates

TS Date 05 May 2023
Estimate Approval 05 May 2024
NIT Approval 05 May 2023
Tender Closing 22 May 2023
Technichal Pre-Qualification 22 May 2023
Price bid opening 23 May 2023

Approval Dates

Workorder Date 22 Aug 2023
NA 21 Oct 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thaliparamba WS Sub Dn
Date: 27/06/2025

Work in progress | 20% Completed

OHSR Pakkanhikkad -Structrual work completed. OHSR Kattayal- Ground levelling completed. Pipe laying 30km completed..

Thaliparamba WS Section
Date: 19/06/2025

Work in progress | 20% Completed

OHSR Pakkanhikkad -Structrual work completed. OHSR Kattayal- Ground levelling completed. Pipe laying 30km completed..