Project | JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 2.00 LL Sump at Edakkome, Supplying and laying pumping main from Booster station at Edakkome to OHSR at Vilayarkode, Construction of 3.00LL OHSR at Vilayarkode, Supplying and laying transmission main from Vilayarkode to Pakkanhikkad OHSR, Supplying and laying distibution network for Zone-I and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package I |
---|---|
Project Code | KNRJJM022213765P1 |
Type | Package |
Main Project | Jal Jeevan Mission-Kannur District - Chapparappadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II - Providing FHTCs Thimiri - Vellad Villages |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | JJM-Kannur District- Chapparapadavu Panchayath - JICA WSS to Pattuvam and Adjoining villages Phase II- Supplying and laying transmission main, Construction of 2.00 LL Sump at Edakkome, Supplying and laying pumping main from Booster station at Edakkome to OHSR at Vilayarkode, Construction of 3.00LL OHSR at Vilayarkode, Supplying and laying transmission main from Vilayarkode to Pakkanhikkad, Supply & Erection of Pumpsets, Supplying and laying distibution network for Zone-I and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works-Package I |
Status | On-going |
District | Kannur |
Executing Office | Thaliparamba WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 189900000 |
TS Number | 959/2023-24 |
Technical specification | Supplying and laying transmission main, Construction of 2.00 LL Sump at Edakkome, Supplying and laying pumping main from Booster station at Edakkome to OHSR at Vilayarkode, Construction of 3.00LL OHSR at Vilayarkode, Supplying and laying transmission main from Vilayarkode to Pakkanhikkad, Supply & Erection of Pumpsets, Supplying and laying distibution network for Zone-I and providing FHTCs, LSGD road reformation works and PWD, KRFB road reformation works |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/04/2023 |
---|---|
Scheduled date of Completion as per agreement | 26 Aug 2024 |
Expected date of Completion | 31/08/2024 |
TS Date | 12 Apr 2023 |
---|---|
Estimate Approval | 12 Apr 2023 |
NIT Approval | 12 Apr 2023 |
Workorder Date | 01 Aug 2023 |
---|---|
NA | 17 Aug 2023 |
Thaliparamba WS Dn EE |
Date: 05/07/2025 |
Work in progress | 71% Completed
50mm DI K9 PIPE-2698.5M ,200MM DI K9 PIPE-2596M,100 MM DI-3650 M,160MM PVC 8KG/CM2-1883M,90MMPVC 12.5KG/CM2-2073M, 90MMPVC 10KG/CM2-3757M,90MMPVC 8KG/CM2-9107M,63MMPVC 6KG/CM2-1808M,50MMPVC 10KG/CM2-3000M,40MMPVC 10KG/CM2-2200M ETC SUPPLIED TILL DATE. Package-1 Edakkome 2.0 LL sump slab concrete completed and pump house work in progress. 3LL OHSR Tank concrete completed at vilayarkod , pipe laid 160 mm PVC 1218 meter,90 PVC 6769, 50mm PVC 900 meter,200 mm DI 2139.8 meter,250 mm DI 3830.2 meter,100 mm DI 1386.9 meter .
Thaliparamba WS Dn EE |
Date: 01/07/2025 |
Work in progress | 71% Completed
50mm DI K9 PIPE-2698.5M ,200MM DI K9 PIPE-2596M,100 MM DI-3650 M,160MM PVC 8KG/CM2-1883M,90MMPVC 12.5KG/CM2-2073M, 90MMPVC 10KG/CM2-3757M,90MMPVC 8KG/CM2-9107M,63MMPVC 6KG/CM2-1808M,50MMPVC 10KG/CM2-3000M,40MMPVC 10KG/CM2-2200M ETC SUPPLIED TILL DATE. Package-1 Edakkome 2.0 LL sump slab concrete completed and pump house work in progress. 3LL OHSR Tank concrete completed at vilayarkod , pipe laid 160 mm PVC 1218 meter,90 PVC 6769, 50mm PVC 900 meter,200 mm DI 2139.8 meter,250 mm DI 3501.60 meter,100 mm DI 1386.9 meter .